The construction works for UPGRADING OF THE SUBOTICA WASTEWATER TREATMENT PLANT and WASTE WATER PUMPING STATION PALIC are progressing well, in accordance with Contracts signed 11.06.2020. between PUC “Vodovod i Kanalizacija”, Subotica, and company “Graditelj-NS” DOO from Novi Sad.
Components of contract for UPGRADING OF THE SUBOTICA WWTP are:
- Construction and installation of a phosphor polishing stage, comprising of pumping stations, FeCl3 dosing station, static mixer, flocculation and rotating disc filter;
- General overhaul of the existing sludge dewatering table and belt sludge press;
- Supply and installation of bulk water meters;
- Construction of a canopy over the sludge loading area.
- Start date 20.07.2020
- End date: 21.04.2021
Components of contract for WWPS PALIC are:
- Supply, delivery, and construction of wastewater pumping station
- Reconstruction of existing lagoon and conversion of one half into a retention for receiving diluted water during heavy rainfalls;
- Auxiliary installations.
- Start date 20.07.2020
- End date: 21.04.2021