Location
Lake Palic and Lake Ludas are typical shallow Pannonian lakes located in the North of Serbia, in Subotica municipality. The lakes are situated on either side and close to the motorway M22. They can be conveniently reached by a 1½-hour drive from Novi Sad and in 2½-hours from Belgrade. The Hungarian border is just 20 min away.
Hydrology
Lake Palic has the shape of a mirrored “L”, is approx. 8 km long and up to 1 km wide and a surface area of 556 ha.
It is on average 2.5-3 meters deep, with a maximum depthof 3.5 meters. Lake Ludas has the shape of a “T” with a length of about 4.5 km, a width of up to 2 km and a surface area of 380 ha.
It is on average 1m deep, with amaximum depth of 2 meters.
Time Schedule
Project start: 10.09.2018
Project duration: 51 months including extension
Project end: 30 November 2022
The project has been extended from originally 33 to 51 months due to delays caused by the Covid-19 pandemic and due to an increase of the investment budget.
The Situation at project start
Lake water quality and fish population: Regular lake monitoring is performed by the Subotica Public Health Institute. Data show that after commissioning of the modern Subotica wastewater treatment plant (WWTP) pollution values in the lakes have dropped. The WWTP is designed for nutrient removal which means that not only carbon substances (COD and BOD5) are removed, but also nitrogen (N) and phosphorus (P). Both elements must be available at high concentrations in water, that eutrophication can happen. High N and P enable excessive growth of algae which leads to algae bloom (blue or red color of the lake).
The high biological activity uses up the free oxygen in water, causes high turbidity (reduced transparency) which in turn eventually leads to massive fish kills. Only certain types of fish are able to survive in such an environment leading to a reduction of biodiversity and domination of one fish species. As a result of this, the Prussian carp (colloquially “babushka”) which is not a native (autochthon) species in these lakes, has massively developed in population.
Experts estimate that the fish biomass in Lake Palic is about 150 tons, whereby a healthy population would be less than half of this. A pilot fishing campaign performed in 2016 revealed that more than 90% of it is babushka.
The treated wastewater discharged from the Subotica wastewater treatment plant (WWTP) constitutes approx. 2/3 of the inflow to Lake Ludas, the rest is surface and groundwater inflow from the nearby area. The lake volume is about 10 Million m³ and water exchange takes about 7-8 months. Therefore, the quality of the WWTP effluent is of utmost importance for the water conditions in Lake Ludas. The Tisa-Palic Channel was completed in 1995 with the purpose of pumping water from the Tisa River to Lake Palic – which turned out to be uneconomic and is therefore not in use.
The Palic-Ludas Channel constitutes the outflow of Lake Palic and the main inflow to Lake Ludas. Obviously, the water quality of Palic influences that of Ludas. Lake Ludas discharges into the Kereš River which is a tributary to the Tisza River which in turn discharges into the Danube.
Project Objectives
The overall objectives of the project “Biodiversity and Water Protection Lake Palić and Lake Ludaš” are
a) the protection of the biodiversity in the lake area Palić -Ludaš and
b) the promotion of tourism.
Current Situation and Project Progress
WWTP upgrading: Construction of the phosphorus polishing stage comprising of the pumping station, phosphorus precipitation plant and state-of-the-art rotating disc filters has been completed. The test operation started in September 2021 and the plant is in operation. Bulk flow meters were installed which allow establishing a precise water balance and phosphorus balance of the WWTP. The sludge dewatering facilities were generally overhauled and a canopy was built over the sludge loading area to avoid rain diluting the dewatered sludge. A hook loader truck and containers were procured so that PUC can transport the dewatered sludge to the regional landfill, where it is used for producing compost. An emergency response plan has been developed to enable PUC to react quickly in case of an emergency at the WWTP in order to minimise potential phosphorus spills to Lake Palic. Through all these measures the phosphorus discharge to Lake Palic will be significantly reduced.
Palic WWPS: construction of the wastewater pumping station was completed. Since the beginning of August, the wastewater of Palic is pumped to the Subotica WWTP and treated there. Special water hammer equipment was installed to protect the 5 km long pumping main from hydraulic damages. The pumping station was taken over by PUC in September 2021, followed by a period of testing and optimization. The pumping station is in operation.
Palic sewerage: The construction of an 18.6 km sewer network was originally planned; 21.9 km were actually constructed and works were completed in October 2020 and more than 600 house connections were made.
Construction of buffer zones: Construction works for the buffer zones (green belt) around Lake Palic and Lake Ludas works were completed in November 2021. A long construction period was required, since planting trees and bushes is only possible in spring and autumn. Watering of the trees and bushes and cutting of grass and invasive plant species continues. Machines and equipment (tractor, multi-purpose machine, trailer, mowing machines etc.) have been procured for maintaining the buffer zone, and PE Palic-Ludas is intensively using it. Construction of bird watchtowers and rest areas was completed in September 2021 and the facilities are well accepted by visitors. Information boards and booklets on birds, fish and plants were installed at strategic locations. They are equipped with QR codes who link the visitor with the project website where detailed information on each species is provided. The construction of foot paths and bicycle lanes has been completed in June 2021. 2214 meters were originally planned and 2690 meters have actually been constructed. Right from the date of completion, the facilities have been intensively used by the local population and by visitors. In April 2022, PE Palic-Ludas received a 4WD double cabin pick-up maintenance vehicle for transport of staff, tools and material.
Biomanipulation: A specialised fishery boat, 8 trap nets and other fishery equipment were procured and are now used by PE Palic-Ludas for selective fishing. Very successful elective fishing campaigns were performed in 2019, 2020, 2021, 2022 and will continue in future, as it is necessary to control the population of the Prussian Carp (Babuska). More than 240 tons of Babuska were landed until spring 2022. This fish species is not native in the region and reproduces massively if not continuously controlled by selective fishing; an overpopulation of the fish negatively affects the water quality. As part of the project, scientific research was done by the Scientific Institute of Veterinary Medicine of Serbia, led by Dr Vladimir Radosavljevic. It was possible to clearly prove that the seasonal fish kill of the Prussian carp is caused by an outbreak of the herpesvirus hematopoietic necrosis (HVHN) and is not related to the water quality. The virus affects only the Prussian carp, not the other fish species in the lake and is not harmful to human beings. Lake monitoring equipment incl. an electric driven dinghy was procured and handed over to PE Palic-Ludas in October 2020.
The investment period of the project has been extended till November 2021 due to COVID restriction measures and an increased investment budget. The lake monitoring by the project will continue till the end of 2022. In parallel, the Faculty of Forestry of the University of Belgrade performs scientific monitoring of the buffer zone vegetation.
Due to the long turn-over period of the lake body and the years needed by the plants in the buffer zone to fully develop, the positive effects of all the above measures on the biodiversity, the water quality and on tourism in the lake area will be fully visible only after several years.
Project Activities / Scope of Works
The project activities are split into A – Investment measures and B – Accompanying measures.
Services A – Investment Measures:
A1 – Upgrade of the Subotica wastewater treatment plant (WWTP)
A2 – New wastewater pumping station in Palic and pumping main to Subotica
A3 – Extension of the sewerage system in Palic
A4 – Construct buffer zone around Lake Palic and Lake Ludas with bicycle lanes, visitor viewpoints
A5 – Perform biomanipulation on Lake Palic.
Services B – Accompanying Measures
B1 – Technical Assistance to PUC “Water and Sewerage” Subotica, including monitoring industrial discharges, strategy for emptying septic tanks, tariffs, PR activities
B2 – Technical Assistance to PE “Palic-Ludas”, including buffer zone operation & maintenance, sources of income to finance buffer zone maintenance, PR activities
B3 – City of Subotica, including groundwater monitoring, establish project website, environmental education, cooperation with tourism associations, the involvement of NGOs, PR activities
Budget and Financing
6.5 Million EUR (approx. 780 Million RSD) grant financing from the Government of Germany, administered by the KfW Entwicklungsbank, plus additional 1.3 Mill. EUR (approx. 153 Million RSD).
1.0 Million EUR (approx. 120 Million RSD) by Local Government (City of Subotica) for land acquisition and compensation payments and contributions in kind.